Policy

Default start time

Specifies the start time that Project assigns to tasks by default when you enter a start date without specifying a time. If you enable this setting, new tasks where the user does not enter a start time will use the start time that you specified. If you disable or do not configure this setting, the user's default setting is used.

Policy
Pack Microsoft Office
Category Microsoft Project 2016 / Project Options / Calendar
Policy ID b97544e673f9
Internal name L_PjDefaultStartTime

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calendar\default start time

Policy notes

Specifies the start time that Project assigns to tasks by default when you enter a start date without specifying a time. If you enable this setting, new tasks where the user does not enter a start time will use the start time that you specified. If you disable or do not configure this setting, the user's default setting is used.

Related policies