Automatically add new resources and tasks

Automatically adds new resources to the resource pool and assigns them default values whenever a new resource name or new resource's initials are added. If you enable this setting, new resources and tasks are automatically inserted into the project. If you disable this setting, users are alerted whenever a new resource or task is created when making a new assignment. If you do not configure this setting, the user's default setting is used.

Policy
Pack Microsoft Office
Category Microsoft Project 2016 / Project Options / General / General options for 'Project1'
Policy ID e21991272ecd
Internal name L_PjAutoAddNew

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\general\auto add resources (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\general\auto add resources (disabled) = 0

Policy notes

Automatically adds new resources to the resource pool and assigns them default values whenever a new resource name or new resource's initials are added. If you enable this setting, new resources and tasks are automatically inserted into the project. If you disable this setting, users are alerted whenever a new resource or task is created when making a new assignment. If you do not configure this setting, the user's default setting is used.