Moves the completed portion of a task forward to finish at the status date. If you enable this setting, the completed portion of the task moves forward to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.

Policy
PackMicrosoft Office
CategoryMicrosoft Project 2016 / Project Options / Calculation / Calculation options for 'Project1'
Policy ID65e4a3e166a7
Internal nameL_PjAndMoveCompleted

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\andmovecompleted (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\andmovecompleted (disabled) = 0

Policy notes

Moves the completed portion of a task forward to finish at the status date. If you enable this setting, the completed portion of the task moves forward to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.