Edits to total task % complete will be spread to the status date

Distributes the changes to total percent complete evenly across the schedule to the project status date (or to the current date if you haven't specified a project status date). If you enable this setting, edits to total task percent complete are evenly distributed across the schedule up to the status date. If you disable or do not configure this setting, the user's default setting is used.

Policy
Pack Microsoft Office
Category Microsoft Project 2016 / Project Options / Calculation / Calculation options for 'Project1'
Policy ID e544e7642765
Internal name L_PjEditstoTotalTask

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\edits to total task %complete will be spread to the status date (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\edits to total task %complete will be spread to the status date (disabled) = 0

Policy notes

Distributes the changes to total percent complete evenly across the schedule to the project status date (or to the current date if you haven't specified a project status date). If you enable this setting, edits to total task percent complete are evenly distributed across the schedule up to the status date. If you disable or do not configure this setting, the user's default setting is used.