Moves the completed portion of a task back to finish at the status date. If you enable this setting, the completed portion of the task moves back to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.

Policy
Pack Microsoft Office
Category Microsoft Project 2016 / Project Options / Calculation / Calculation options for 'Project1'
Policy ID 6aab06bfde04
Internal name L_PjMoveCompleted

Registry

Copy registry mappings

HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\movecompleted (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\movecompleted (disabled) = 0

Policy notes

Moves the completed portion of a task back to finish at the status date. If you enable this setting, the completed portion of the task moves back to finish at the status date. If you disable or do not configure this setting, the user's default setting is used.

Related policies