Policy
Move start of remaining parts before status date forward to status date
Moves remaining portions of a task forward to start at the status date. If you enable this setting, the remaining portion of the task moves forward to start at the status date. If you disable or do not configure this setting, the user's default setting is used.
Pack Microsoft Office
Category Microsoft Project 2016 / Project Options / Calculation / Calculation options for 'Project1'
Policy ID
96304c60da8c Internal name
L_PjMoveRemaining Registry
Copy registry mappings
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\moveremaining (enabled) = 1
HKCU\software\policies\microsoft\office\16.0\ms project\options\calculation\moveremaining (disabled) = 0 Policy notes
Moves remaining portions of a task forward to start at the status date. If you enable this setting, the remaining portion of the task moves forward to start at the status date. If you disable or do not configure this setting, the user's default setting is used.
Related policies
Actual costs are always calculated by Microsoft ProjectAnd move end of completed parts forward to status dateAnd move start of remaining parts back to status dateCalculate multiple critical pathsDefault fixed costs accrualEdits to total actual cost will be spread to the status dateEdits to total task % complete will be spread to the status date